当前位置:在线题库搜索>[单选题]● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.的答案是什么?

问题:

[单选题]● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.

A、(74)the project is ahead of its planned schedule
B、less work was completed than was planned
C、the cost overrun for work completed
D、the cost under-run of performance to date

参考答案: B