当前位置:在线题库搜索>[单选题]Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.的答案是什么?

问题:

[单选题]Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

A、PERT
B、Resource levelling
C、Schedule compression
D、Critical chain method

参考答案: D