当前位置:在线题库搜索>[单选题] ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.的答案是什么?

问题:

[单选题]

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

A、Planned value
B、Earned value
C、Actual cost
D、Cost variance

参考答案: C