[单选题]● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

A、(73) change the scope baseline
B、contact the customer to determine if the change adds value
C、call a meeting of the change control board
D、change the project' s objectives

参考答案: B